Weeks 4-7: The February 22nd 2011 M6.3 earthquake and the start of the repair of the Christchurch distribution network.
![Image](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEh1bS_Zpj75QrWRXWt-N3IRLCP4OhlXd_BWqZe4SQADfN8uXRrwsgIQVqL5A6gzAFQRvQqLHGiJIhQPi4CXqDLjWpPYV1hZJN-Ziwg4b93A4lqr5_UgHYhyFwd7tEOJgH63LK0wiWpXvY4/s320/Cathedralok.jpg)
This post covers the week of the Christchurch Magnitude 6.3 earthquake and following to Friday the 18th March, the Memorial day. Work log: Monday 21st: Worked with Reece at Nunweek park hockey park terminating 11kV XLPE into a kiosk. Tuesday 22nd: Attempted to finish the kiosk with Reece. Job abandoned for technical reasons. Mag 6.3 Quake hit at 12:51pm. Wednesday 23rd February - Monday 7th March - No work - Quake recovery. Monday 7th: Averill St 11kV quake damaged PILCA-XLPE -PILCA repair with Steve. The post-22 Feb quake 'job desk' at Connetics Connetics and associated supply industry workers at a promotional BBQ breakfast My first quake casualty-11kV previously joined cable in sewer-filled hole.. nice. Faulty quake-bent 11kV PILCA cable, River Road. Steve jointing 11kV Averill St with the hard case boys from Transfield, T and Peachy. Tuesday 8th: Palmers Road 11kV severe quake damaged PILCA-XLPE-PILCA-XLPE-PILCA with Steve The ...